Modernization of the transport system control of the production system
Modernization of the transport system of the production system MPS 500. Creation of a new control program in the environment of the TIA portal. The main functions of the frequency converter. Investigation of the final state of the control cabinet.
Рубрика | Производство и технологии |
Вид | статья |
Язык | английский |
Дата добавления | 26.08.2020 |
Размер файла | 761,3 K |
Отправить свою хорошую работу в базу знаний просто. Используйте форму, расположенную ниже
Студенты, аспиранты, молодые ученые, использующие базу знаний в своей учебе и работе, будут вам очень благодарны.
Размещено на http://www.allbest.ru/
Modernization of the transport system control of the production system
Patrik Sarga, Tomas Zaboly
Festo MPS 500 (Fig. 1) is an educational modular production system that helps to teach mechatronics and automation [1]. It consists of a central transport system (conveyor), process station, entry and exit station and assembly station with a robot. The transport system (Fig. 2) is the brain of the MPS 500. Transport trolleys are used to move the assembled components on the line. Up to 4 components can be placed on each trolley. All stations are interconnected with the transport system. Control of the stations and transport system is conducted by programmable logic controllers (PLCs). Communication between individual stations and the conveyor is ensured via I/O (input / output) ports and AS-i (Actuator / Sensor interface) [2], [3].
Fig. 1. Festo MPS 500: 1 - distribution and testing station, 2 - process station, 3 - assembly station with a robot, 4 - handling and sorting station, 5 - transport system
Fig. 2. Transport system of the MPS 500
All control elements of the transport system, including the PLC, frequency converter for motors and cabling, are located in the control cabinet. All these elements are supplied via the safety relay contacts. The original state of the control cabinet of the educational system MPS 500 before its modernization is shown in Fig. 3.
Fig. 3. The original state of the control cabinet:
1 - PLC Siemens SIMA TIC S7-300 CPU 313c; 2 - Frequency converter Siemens MICROMASTER 420;
3 -Power supply unit; 4 - Safety relay pilz x9
Modernization of the transport system. The main criterion in the modernization of the transport system of the MPS 500 was the use of modern components following Industry 4.0 [4]. MPS 500 is modular, so it can be extended to include stations that would perform other operations, such as monitoring by a smart camera. With the camera, it is possible to monitor the correct machining of the component or to monitor the status of the component storage station. Later, it will be possible to extend the MPS 500 with sensors for detection of the trolley's presence, the presence of a component on the trolley, or the filling of the conveyor in front of the station.
Control system. Before the actual expansion of the MPS 500, it was necessary to upgrade the control by PLC. Since we decided to use the Profinet communication bus, it was necessary to use a switch with a suitable number of communication ports to connect the PLC with each station. The control PLC must communicate with the stations and synchronize them with the conveyor belt.
We chose the PLC S7-1500 CPU 1512C-1PN (Fig. 4) [5] as the control PLC. An important indicator for selecting a PLC was the fact that it has up to 32 I/O ports for further system expansion. Plus of the selected PLC is an integrated web server, which offers the possibility to display diagnostic and service information remotely. This PLC also has five analogue inputs that can be used to collect information from current, temperature, and other relevant sensors.
The SIMATIC S7-1500 PLC has two Profinet communication ports. This communication bus will also allow the system to access the Internet and connect it to the cloud. Another reason why we decided to use the SIMATIC S7-1500 PLC was that the lower-order PLC does not have enough computational power to process the amount of data retrieved from the sensors.
Fig. 4. PLC Siemens SIMATIC S7-1500 CPU 1512C-1PN [5]
The PLC does not provide a direct connection of the communication module, so it was necessary to use a decentralized peripheral. Siemens offers the SIMATIC ET 200 peripheral for this purpose.
SIMATIC ET 200 offers a wide range of distributed I/O systems. There is a version installed in the control cabinet or without the control cabinet, installed directly in harsh industrial environments. The device is also available with the protection up to IP67. [6]
A SIMATIC ET 200SP with IP20 protection was used for our needs (Fig. 5). It is easy to operate, ensuring maximum economy in a switchboard with a compact design and high performance [7].
Fig. 5. SIMATIC ET 200SP [7]
To the decentralized peripheral SIMATIC ET 200SP, it was also necessary to connect an additional module AS-i Master, which is a communication module for AS-Interface. The AS-i master allows simple “field” devices to be connected to the SIMATIC ET 200SP via the AS- Interface. Several AS-i Master modules can be connected to one SIMATIC ET 200SP. [8]. Fig. 6 shows the ET 200SP peripheral with AS-i mastic attached.
Fig. 6. SIMATIC ET 200SP with AS-i Master [8]
Frequency converter. SINAMICS G120 from Siemens has been selected from the offer of frequency converters (Fig. 7). It is a modular frequency converter for a variety of asynchronous motor control applications. Various converter variants allow a wide power range from 0.55 to 250kW. This series of converters are available in three voltage variants for connection to 200V, 400V and 690V. Each SINAMICS G120 series frequency converter consists of a control unit and a power unit. In the SINAMICS G120 series, each control unit can be combined with each power unit.
The control unit controls and monitors the power unit and the connected motor with the choice of the control method. It enables communication with central or local control as well as with monitoring devices.
Fig. 7. Frequency converter Siemens SINAMICS G120 [9]
Basic functions of the SINAMICS G120 converter [10]:
vector, torque control with or without speed feedback, precise stopping for a defined number of shaft (engine) revolutions, possibility to measure speed, frequency, current, temperature, torque, voltage, motor power, fixed power frequency or potentiometer for setting the engine speed, diagnostics and fault reporting, an automatic slow start after failure, adjustable switching frequency for silent motor operation.
Installing new components. New components have been installed in the control cabinet - PLC, decentralized peripheral SIMATIC ET 200SP, frequency converter SINAMICS G120 and SCALANCE X208 switch for interconnection of all PLCs used on the system MPS 500. These devices are mounted on a DIN rail. It was also necessary to connect the 24V power supply to the SIMATIC ET 200SP. Subsequently, AS-i master and the PLC were connected with a network cable to SIMATIC ET 200SP. The final state of the control cabinet is shown in Fig. 8.
Fig. 8. The final state of the control cabinet: 1 - PLC Siemens SIMA TIC S7-1500 CPU 1512C-1PN; 2 - SIMA TIC ET 200SP; 3 - Switch SCALANCEX208; 4 - Frequency converter Siemens SINAMICS G120
The control program. After the hardware changes were made, it was necessary to create a new transport system control program to work with all stations in the MPS 500. The transport system must be able to respond to any conditions that may occur during MPS 500 operation (such as empty trolley in front of the station). The control program was created in TIA Portal in the LAD programming language.
TIA Portal (Totally Integrated Automation Portal) is Siemens software designed to create custom applications for PLCs, distributed peripherals, network components and communication components, HMI (human machine interface) panel design and extensive SCADA (Supervisory control and data acquisition) visualizations. All of this is integrated into a single software environment with an easy single-screen operation.
TIA Portal not only accelerates the creation of user applications but also has a transparent and straightforward structure. The resulting control program can be easily modified or supplemented. The program allows more accessible diagnostics in regular operation, including maintenance and service of automation technology. With its characteristic system features, TIA Portal supports the complete life cycle of the machine or devices [11].
Fig. 9 shows a demonstration of a control program that ensures the transport system cooperates with an assembly station with a robot.
Experimental verification of system functionality. The testing was carried out to verify the functionality of the whole system MPS 500. It was necessary to test all possible scenarios that might occur while the program was running in order to correct errors in the control program. The production cycle time required to test, process, assemble and sort one component was also measured. The identified shortcomings were subsequently remedied, and the resulting solution is fully operational [12]. transport production converter frequency
Fig. 9. Part of the control program
Conclusions
The main aim of this work was to modernize the transport system of the educational line MPS 500. Elements of the system management were changed, and a new control program was created in the TIA Portal environment. Used PLC and decentralized peripherals SIMATIC ET 200SP fulfil their task without problems, and the control of the movement of transport trolleys is performed as expected. All stations were connected via Profinet via SCALANCE X208 switch. The Siemens SINAMICS G120 frequency converter can measure current, temperature or torque values directly. The inverter has a port for connection to the PLC via Profinet, that is, it sends the measured values directly via the data cable to the PLC, which processes them. It is also possible to parameterize the converter centrally via the PC, thus avoiding time-consuming parameter entry via the display or by using the buttons on the converter.
The next step in extending MPS 500 functions will be to implement an HMI panel on which will be the process visualized. The HMI panel also has a Profinet connection so it can be connected to the PLC via free ports on the switch. In the next phase, the MPS 500 will be supplemented with additional sensors to monitor multiple parameters. The MPS 500 also connects to the cloud, allowing remote control of the production process
Acknowledgement. This work was supported by grant project VEGA 1/0330/19.
References
1. Schober, (2012), FESTO MPS500 manual, Denkendorf, 52 p [in English]. AS-INTERFACE (2019)
2. Simsik, Dusan (2019): Zвklady automatizвcie, Kosice [in Slovak].
3. Zвboly, Tomвs (2019): Nвvrh a realizвcia riadenia asynchronneho motora pre dopravny sys- tйm experimentвlnej linky, Kosice, [in Slovak].
Abstract
Urgency of the research. Nowadays, it is crucial to keep up with modern technologies. Therefore, this work aims to modernize the production system Festo MPS 500. Thanks to this, it will be possible to apply to the system technologies meeting the latest trends in Industry 4.0. The MPS 500 system prepared in this way can be used to research new trends in accordance with Industry 4.0. The modernized MPS 500 system will also find use in the education of students in the field of automation and mechatronics so that they are sufficiently prepared for practice.
Target setting. The goal of the research was to modernize the transport system of the modular production system Festo MPS 500 according to Industry 4.0platform.
Actual scientific researches and issues analysis. When upgrading the system MPS 500 and preparing this paper, we took into account both current sources - publications and papers dealing with the current state of Industry 4.0 and modular production systems as well as existing modular production systems based on Industry 4.0 platform.
Uninvestigated parts of general matters defining. At this stage of the research, data acquisition from the system MPS 500 and interconnection with the cloud was not realized.
The research objective. The purpose of this article is to modernize the MPS 500, which will allow focusing on Industry 4.0 research specifically for the deployment of Cyber-physical systems, Internet of Things, Big Data, Cloud Computing.
The statement of basic materials. Effective research of the new technologies in the industry requires to use modern systems which meet the criteria ofIndustry 4.0 platform. So the original system Festo MTS 500 was upgraded by systems from Siemens.
Conclusions. The main aim of this work was to modernize the transport system of the production system MPS 500. Elements of the system management were changed, and a new control program was created in the TIA Portal environment. The functionality of the MPS 500 was subsequently verified, where the full functionality of the system was confirmed. It makes the MPS 500 ready for further expansion in accordance with Industry 4.0.
Keywords: automation; control; modular production system; transport system; PLC; Industry 4.0.
Актуальність теми дослідження. В даний час, вкрай важливо, щоб йти в ногу з сучасними технологіями. Отже, ця робота спрямована на модернізацію виробничої системи Festo MPS 500. Завдяки цьому можна буде застосувати до системних технологій, що відповідають останнім тенденціям у Індустрії 4.0. Підготовлена таким чином система MPS 500 може бути використана для дослідження нових тенденцій відповідно до Індустрії 4.0. Модернізована система MPS 500 також знайде застосування у навчанні студентів у галузі автоматики та мехатро- ніки, щоб вони були достатньо підготовлені до практики.
Постановка проблеми. Метою дослідження була модернізація транспортної системи модульної виробничої системи Festo MPS 500 відповідно до платформи Індустрія 4.0.
Аналіз останніх досліджень і публікацій. Під час оновлення системи MPS 500 та підготовки даного документу ми врахували як сучасні джерела - публікації та статті, що стосуються сучасного стану Індустрії 4.0, так і модульні виробничі системи, а також існуючі модульні виробничі системи на базі платформи Індустрія 4.0.
Виділення недосліджених частин загальної проблеми. На даному етапі досліджень збір даних із системи MPS 500 та взаємозв'язок з хмарою здійснено не було.
Постановка завдання. Метою цієї статті є модернізація MPS 500, що дозволить зосередитися на дослідженнях Індустрії 4.0 теціально для розгортання кіберфізичних систем, інтернетуречей, великих даних, хмарних обчислень.
Виклад основного матеріалу. Ефективне дослідження нових технологій у галузі потребує використання сучасних систем, що відповідають критеріям платформи Індустрія 4.0. Отже, оригінальна система Festo MTS 500 була модернізована системами виробництва Siemens.
Висновки відповідно до статті. Основна мета цієї роботи полягала в модернізації транспортної системи виробничої системи MPS 500. Елементи управління системою були змінені та створено нову програму управління в середовищі порталу TIA. Потім функціональність MPS 500 була перевірена, де була підтверджена повна функціональність системи. Це робить MPS 500 готовим до подальшого розширення відповідно до Індустрії 4.0.
Ключові слова: автоматизація;управління; модульна виробнича система; транспортна система; PLC; Індустрія 4.0.
Размещено на Allbest.ru
Подобные документы
Технологічний процес роботи автоматичної установки для сушіння вологого матеріалу сільськогосподарського призначення – бурячного жому. Застосування логічного мікропроцесорного контролера VIPA SYSTEM 200V, контури контролю та регулювання процесів.
курсовая работа [1,7 M], добавлен 07.12.2011Методы защиты окружающей среды от опасных техногенных воздействий промышленности на экосистемы. Структура и функциональные особенности автоматизированной системы контроля окружающей среды, принципы ее эксплуатации. Робот-медуза Oceanic Cleaning System.
реферат [186,3 K], добавлен 30.03.2014Описание технологического процесса фракционирования углеводородного сырья. Схема дисцилляции — фракционирования нефти. Регулирование уровня мазута в кубе ректификационной колонны. Обработка массива данных с помощью пакета System Identification Toolbox.
курсовая работа [2,4 M], добавлен 28.05.2015Расчет и конструирование двигателя, выбор главных размеров, расчет обмотки статора. Расчет размеров зубцовой зоны статора и выбор воздушного зазора. Моделирование двигателя в среде MatLab Power System Blockset а также с параметрами номинального режима.
курсовая работа [331,3 K], добавлен 25.09.2009The popular explanation of lift The wing as a pump. Lift as a function of angle of attack. The wing as air "scoop". Axis of Rotation Forces. Flight Control Surfaces. History of Laminar Flow. The B-24 bomber's "Davis" airfoil was a laminar flow airfoil.
курсовая работа [3,4 M], добавлен 08.07.2009Investigation the relationship for the extension of spiral spring and for the oscillation period of this spring of suspended different mass. Earth Gravitational Intensity. The results of load mass and reading on ruler. Measurement error and calculations.
реферат [209,9 K], добавлен 17.10.2014Initial data for the term paper performance. Order of carrying out calculations. Analyze uncompensated system. Synthesize the real PD-compensator ( ) which would guarantee desired phase margin at gain crossover frequency . Analyze compensated system.
курсовая работа [658,7 K], добавлен 20.08.2012Testing as a form of control the level of students’ skills and abilities. The classification of tests in learning English. Problems in the control of education. The final results on the evaluation system of knowledge. The main stage of the lesson.
курсовая работа [37,8 K], добавлен 08.05.2014The cardiovascular system comprises of the heart, blood and lymphatic system. The function of the heart is to pump blood around the body. Three main functions of the blood: transport, regulation, and protection. The protective role of lymphatic system.
презентация [430,1 K], добавлен 02.04.2012Разработка информационной системы Dentist control system для работы стоматологической клиники - ведения записей о клиентах и врачах. Использование средства автоматизированной разработки приложений Borland C++ Builder 6.0 для работы с базой данных.
курсовая работа [2,3 M], добавлен 29.12.2012